Case Number: T13-0084

  • 04/01/2014
    Filing - Report

    Progress report – plans and estimates complete; awaiting clearance of environmental survey request, electronically filed by staff for Brandon Simmons, Jefferson County Highway Engineer.
  • 09/18/2013
    Order Entered - Final

    Copy of Order and Stipulated Agreement entered September 18, 2013 mailed to All Parties of Record
  • 08/20/2013
    Filing - Stipulated Agreement

    Stipulated Agreement #1732 Filed.
  • 08/20/2013
    Filing - Compliance

    Project status report providing employee contact for project (Patrick Jones, CN/IC 708-332-3557, Pat.jones@cn.ca and Brandon Simmons, Jefferson County Highway Department 618-244-8031, countyengineer@jeffil.us), filed with the stipulated agreement.