Case Number: 13-0276

  • 06/27/2013
    Service - Order

    Copy of Final Order served electronically to parties.
  • 06/26/2013
    Order Entered - Final

    Final Order entered.
  • 05/31/2013
    Briefs - On Exceptions

    Brief on Exceptions of Commonwealth Edison Company filed by Rooney Rippie & Ratnaswamy LLP. (electronic)
  • 05/24/2013
    Service - Proposed Order

    Proposed Order served electronically to parties.
  • 05/09/2013
    Service - Administrative Law Judge Ruling

    Notice is hereby given that the schedule the Administrative Law Judges’ issued on May 7, 2013 stands in order to give the parties a chance to respond to Commonwealth Edison Company’s Renewed Verified Motion for Entry of a Protective Order. Notice served electronically to parties.
  • 05/08/2013
    Service - Administrative Law Judge Ruling

    Notice is hereby given by the Administrative Law Judges that they have received the Motion filed by Commonwealth Edison Company for entry of a protective order. This motion is denied at this time because the briefing schedule proposed in that motion does not appear to be consistent with due process. The schedule ordered on May 7th, 2013 regarding entry of a protective order (see below) stands. Any objection to the Petition seeking confidential treatment of portions of ComEd’s annual AMI Implementation Report (filed in docket 13-0276 but affecting docket 13-0285) must be filed and served by May 13, 2013. A Reply, if any, must be filed and served by May 15, 2013. Notice served electronically to parties.
  • 05/07/2013
    Service - Administrative Law Judge Ruling

    Notice is hereby given by the Administrative Law Judges that any objection to the Petition seeking confidential treatment of portions of ComEd’s annual AMI Implementation Report (filed in docket 13-0276 but affecting docket 13-0285) must be filed and served by May 13, 2013. A Reply, if any, must be filed and served by May 15, 2013. Notice served electronically to parties.
  • 04/04/2013
    Filing - Petition/Application

    Petition to Protect Confidential Information in 2013 Advanced Metering Annual Implementation Progress Report, filed by Rooney Rippie & Ratnaswamy LLP on behalf of Commonwealth Edison Company. (Electronic)