Case Number: 12-0566

  • 11/21/2012
    Service - Order

    Copy of Final Order served electronically to parties.
  • 11/20/2012
    Order Entered - Final

    Final Order entered.
  • 10/31/2012
    Filing - Response

    Response of Resolution Power LLC to Administrative Law Judge's Ruling filed by Rowland & Moore LLP. (electronic)
  • 10/25/2012
    Filing - Proof of Publication

    Proof of Publication, filed by Rowland & Moore LLP on behalf of Resolution Power LLC. (Electronic)
  • 10/25/2012
    Service - Administrative Law Judge Ruling

    Notice given that the Administrative Law Judge has completed a preliminary review of the application for an alternative electric supplier ("ARES") certificate filed by Resolution Power LLC (“Applicant”) in Docket No. 12-0566, and hereby rules that the information described below shall be filed with the Chief Clerk of the Illinois Commerce Commission ("Commission") on or before November 2, 2012. The response to this ruling shall be verified and must be actually received by the date indicated, regardless of whether the response is filed with the Chief Clerk electronically or as a hard copy. Applicant shall also electronically serve a Word version of its response on the Administrative Law Judge (jvonqual@icc.illinois.gov) by the date indicated. 1. Subsection 451.30(a) requires Applicant to publish notice of its application in the Official State Newspaper within 10 days following application filing, and to file proof of that publication with the Clerk of the Commission within 5 days after publication.
    If the Applicant has not yet filed the proof of publication with the Clerk of the Commission, it shall file the proof of publication. 2. Paragraph 15 of the application does not clearly state whether Applicant certifies that it will procure renewable energy resources as required by Section 16-115D and Section 16-115(d) of the Act, or that Section 16-115D and Section 15-115(d) do not apply to it pursuant to Section 16-115D(h).
    Applicant shall certify which of the two alternatives applies to it.
    3. On its face the Permit Bond provided as Attachment D to the application indicates that it is a “Sample License or Permit Bond for ARES Applicants."
    Applicant shall file a Permit Bond which does not indicate on its face that it is a Sample. 4. Applicant shall indicate whether it has affiliates. If it has affiliates, Applicant shall indicate whether any of them provide retail electric or gas services and, if so whether any formal complaints have been filed against such affiliates for provision of these services. If formal complaints have been filed, the Applicant shall provide: the nature of the complaint, the jurisdiction and the ultimate resolution or current status of each the complaint. 5. Applicant shall indicate whether it intended for confidential treatment to be given to the organizational chart provided in Attachment I. If Applicant requests confidential treatment, Applicant shall file a motion requesting the treatment and asserting the reasons the chart should be afforded confidential treatment. Notice served electronically to parties.
  • 10/15/2012
    Filing - Petition/Application

    Application for Certificate of Service Authority, filed by Rowland & Moore LLP on behalf of Resolution Power LLC. (Electronic)