Case Number: 08-0519

  • 01/08/2009
    Service - Order

    Copy of Final Order served electronically to parties.
  • 01/07/2009
    Order Entered - Final

    Final Order entered.
  • 12/15/2008
    Service - Administrative Law Judge Ruling

    Notice served electronically advising of the attached Administrative Law Judge's Procedural Ruling. Parties advised electronically.
  • 12/10/2008
    Briefs - Reply to Exceptions

    Reply Brief on Exceptions of Commonwealth Edison Company, filed by Foley & Lardner LLP. (Electronic)
  • 12/10/2008
    Briefs - Reply to Exceptions

    Reply Brief on Exceptions of the Staff of the Illinois Commerce Commission, filed. (Electronic)
  • 12/09/2008
    Briefs - On Exceptions

    Brief on Exceptions of Commonwealth Edison Company, filed by Foley & Lardner LLP. (Electronic)
  • 12/09/2008
    Briefs - On Exceptions

    Brief on Exceptions of the People of the State of Illinois, filed. (Electronic)
  • 12/09/2008
    Briefs - On Exceptions

    Response of The Illinois Power Agency to the Administrative Law Judge's Proposed Order, filed by Kelley Drye & Warren LLP. (Electronic)
  • 12/05/2008
    Service - Proposed Order

    Proposed Order served electronically to parties.
  • 11/19/2008
    Filing - Response

    Response to Notice of Administrative Law Judge's Procedural Ruling, filed by the Ameren Illinois Utilities. (Electronic)
  • 11/19/2008
    Filing - Reply

    Staff of the Illinois Commerce Commission Verified Reply to Certain Responses to Objections to Procurement Plan, filed. (Electronic)
  • 11/19/2008
    Filing - Reply

    Reply of Commonwealth Edison Company to Certain Responses to the Objections to the Procurement Plan of the Illinois Power Agency, filed by Foley & Lardner LLP. (Electronic)
  • 11/18/2008
    Service - Administrative Law Judge Ruling

    Notice is given of the following procedural ruling by the Administrative Law Judge in Docket No. 08-0519:
    The following motions, to which no objections have been filed, are granted:
    Motion filed by the Illinois Power Agency (“IPA”) on November 14, 2008 “for Leave to File an Errata to Its Verified Response to Objections to the Power Procurement Plan”;
    Motion filed by the IPA on November 13, 2008 “Seeking an Enlargement of Time to File its Verified Response to the Objections to its Initial Procurement Plan and its Verification to the October 20, 2008 Procurement Plan” and Motion filed by the Staff of the Illinois Commerce Commission on October 30, 2008 “for Leave to File Sur-Reply to Commonwealth Edison Company’s and the Illinois Power Agency’s Replies to Staff’s Response and Objections.” With regard to any replies (to responses to objections) filed pursuant to the procedural ruling issued November 17, 2008, such responses shall be filed in verified form or supported by affidavit to the extent they include any content other than legal arguments. The instant procedural ruling is concluded. Parties advised electronically.
  • 11/17/2008
    Service - Administrative Law Judge Ruling

    Notice given by the Administrative Law Judge of the attached Procedural Ruling. Parties advised electronically.
  • 11/14/2008
    Filing - Motion

    Illinois Power Agency’s Motion for Leave to File an Errata to Its Verified Response to Objections to the Power Procurement Plan, filed by Kelley Drye & Warren LLP. (Electronic)
  • 11/13/2008
    Filing - Response

    Verified Response of the Illinois Power Agency to Objections to its Initial Power Procurement Plan filed by Kelley Drye & Warren LLP. (electronic)
  • 11/13/2008
    Filing - Motion

    Illinois Power Agency's Motion Seeking an Enlargement of Time to File its Verified Response to the Objections to its Initial Procurement Plan and its Verification to the October 20, 2008 Procurement Plan filed by Kelley Drye & Warren LLC. (electronic)
  • 11/12/2008
    Filing - Response

    Staff of the Illinois Commerce Commission Verified Response to Objections to Procurement Plan, filed. (Electronic)
  • 11/12/2008
    Filing - Response

    Response of Commonwealth Edison Company to the Objections of Other Parties to the Procurement Plan of the Illinois Power Agency, filed by Foley & Lardner LLP. (Electronic)
  • 11/12/2008
    Filing - Comments

    Reply Comments of the Retail Energy Supply Association, filed by Rowland & Moore LLP. (Electronic)
  • 11/12/2008
    Filing - Response

    Verified Response of the People of the State of Illinois to Objections to the Illinois Power Agency's Initial Power Procurement Plan, filed. (Electronic)
  • 11/05/2008
    Filing - Petition to Intervene

    Verified Petition to Intervene of the Coalition of Energy Suppliers, filed by DLA Piper US LLP. (Electronic)
  • 11/05/2008
    Service - Commission Action

    Parties advised electronically of the action of the Commission on November 3, 2008.
  • 11/05/2008
    Service - Administrative Law Judge Ruling

    Notice given of the following procedural ruling by the Administrative Law Judge in Docket No. 08-0519:
    On or before November 12, 2008, verifications or affidavits shall be filed (1) by the Illinois Power Agency (“IPA”), verifying the revised plan and the petition seeking approval thereof which were filed October 21, 2008, and (2) by the Ameren Illinois Utilities (“Ameren”), verifying the objections, filed October 27, 2008, to the revised plan.
    Any responses by the IPA and other Parties to the substantive objections filed October 27, 2008 shall be filed, in verified form, on or before November 12, 2008, and shall be specific to the objections filed by Ameren (1, 2 and 3), Commonwealth Edison Company (I, II, III and IV) and the Illinois Commerce Commission Staff (Section III). Copies shall be served on other parties, and (in Word format) on the Administrative Law Judge, by 5:00 P.M. on the date of filing. Parties advised electronically.
  • 11/03/2008
    Commission Action - General

    The Commission in conference determined, pursuant to 220 ILCS 5/16-111.5(d)(3), that a hearing in the above-referenced matter is not necessary; and (2) directed that a procedural order be issued requiring verifications or affidavits to be filed for the revised plan and the petition seeking approval thereof which were filed October 21, 2008, and for the objections to the revised plan which were filed October 27, 2008 to the extent such filings are not already in verified form; and further requiring that all responses to objections, and any other pleadings, be filed in verified form or supported by affidavit. These actions will be further implemented in a procedural order or ruling by the Administrative Law Judge.
  • 10/30/2008
    Filing - Motion

    Motion for Leave to File Sur-Reply to Commonwealth Edison Company’s and the Illinois Power Agency’s Replies to Staff’s Response and Objections, filed. (Electronic)
  • 10/30/2008
    Filing - Reply

    Staff’s Sur-Reply to Commonwealth Edison Company’s and the Illinois Power Agency’s Replies to Staff’s Response and Objections, filed. (Electronic)
  • 10/28/2008
    Filing - Comments

    Illinois Power Agency's Comments Regarding the Question of Whether the ICC Should Conduct a Hearing to Consider the Procurement Plan, filed by Kelley Drye & Warren LLP. (Electronic)
  • 10/28/2008
    Filing - Motion

    Commonwealth Edison Company's Motion for Leave to File A Reply to the Objections of Staff of the Illinois Commerce Commission, filed by Foley & Lardner LLP. (Electronic)
  • 10/28/2008
    Filing - Reply

    Reply of Commonwealth Edison Company to the Staff's Response and Objections to the Illinois Power Agency's Procurement Plan, filed by Foley & Lardner LLP. (Electronic)
  • 10/27/2008
    Filing - Comments

    Ameren Illinois Utilities' Reply Comments and Objections to the Illinios Power Agency's Initial Procurement Plan, filed. (Electronic)
  • 10/27/2008
    Filing - Objection

    Objections of Commonwealth Edison Company to the Procurement Plan of the Illinois Power Agency, filed by Foley & Lardner LLP. (Electronic)
  • 10/27/2008
    Filing - Response

    Response and Objections to the Illinois Power Agency’s Procurement Plan filed October 20, 2008 by the Staff of the Illinois Commerce Commission, filed. (Electronic)
  • 10/23/2008
    Service - Administrative Law Judge Ruling

    Notice given of the following procedural ruling by the Administrative Law Judge in Docket No. 08-0519:
    Section 16-111.5(d)(3) of the Public Utilities Act, 220 ILCS 5/16-111.5, provides, in part, “Within 5 days after the filing of the procurement plan, any person objecting to the procurement plan shall file an objection with the Commission.” Accordingly, any such “objections” shall be filed on or before October 27, 2008. Copies thereof shall be served electronically on other parties, and (in Word format) on the Administrative Law Judge, by 5:00 P.M. on the date of filing. With regard to such objections, please note that incorporation by reference of any comments “submitted to the [Illinois Power] Agency” (“IPA”) pursuant to Section 16-111.5(d)(2) is not acceptable. Pursuant to Section 16-111.5(d)(2), those comments were submitted to the IPA for review by the IPA, not for review by the Illinois Commerce Commission.
    The instant procedural ruling is concluded. Parties advised electronically.
  • 10/21/2008
    Filing - Petition/Application

    The Illinois Power Agency’s Petition for Approval of the 220 ILCS 5/16-111.5(d) Procurement Plan, filed by Kelley Drye & Warren LLP. (Electronic)
  • 10/15/2008
    Filing - Appearance

    Appearance on behalf of the Illinois Power Agency, filed by Kelley Drye & Warren, LLP. (Electronic)
  • 10/10/2008
    Filing - Petition to Intervene

    Petition for Leave to Intervene of Wind for Illinois, filed. (mailed by USPS - October 9, 2008)
  • 10/10/2008
    Filing - Comments

    Comments of Wind for Illinois to the Illinois Commerce Commission regarding the Illinois Power Agency's 2009 Initial Procurement Plan, filed. (mailed by USPS - October 9, 2008)
  • 10/08/2008
    Filing - Appearance

    Notice of Appearance and Comments of the PJM Power Providers Group, Inc., filed by Chappelle Consulting, LLC. (mailed by UPS Next Day Air - no date noted)
  • 10/08/2008
    Filing - Request

    Request to Gain Pro Hac Vice Status on behalf of PJM Power Providers Group, Inc. and Leave to Intervene, filed by Chappelle Consulting, LLC. (mailed by UPS Next Day Air - no date noted)
  • 10/06/2008
    Filing - Comments

    Comments of Commonwealth Edison Company, filed by Foley & Lardner LLP. (Electronic)
  • 10/06/2008
    Filing - Comments

    Comments On Updated Submittal of Draft Initial Procurement of Plan by the Staff of the Illinois Commerce Commission, filed. (Electronic)
  • 10/06/2008
    Filing - Appearance

    Appearance of the American Wind Energy Association, filed. (Electronic)
  • 10/06/2008
    Filing - Comments

    Comments of Constellation Energy Commodities Group, Inc. and Constellation NewEnergy, Inc. Concerning the Illinois Power Agency’s Petition for Approval of Initial Procurement Plan, filed. (Electronic)
  • 10/06/2008
    Filing - Comments

    Comments on behalf of Midwest Generation, LLC and Edison Mission Marketing & Trading, Inc. to the Updated Draft Initial Power Procurment Plan of the Illinois Power Agency, filed by Attorney Rebecca J. Lauer. (Electronic)
  • 10/06/2008
    Filing - Motion

    Motion to Appear Pro Hac Vice, filed by The American Wind Energy Association. (Electronic)
  • 10/06/2008
    Filing - Comments

    Comments of the The American Wind Energy Association on the Renewable Energy Portfolio Proposed by the Illinois Power Agency, filed. (Electronic)
  • 10/06/2008
    Filing - Petition to Intervene

    Petition to Intervene of the Retail Energy Supplier Association, filed by Rowland & Moore LLP. (Electronic)
  • 10/06/2008
    Filing - Comments

    Joint Comments of
    the People of the State of Illinois, the City of Chicago, the Citizens Utility Board, the
    Environmental Law & Policy Center, the Natural Resources Defense Council, and
    the Environment Illinois Research and Education Center on the Initial Power
    Procurement Plan Proposed by the Illinois Power Agency, filed. (Electronic)
  • 10/06/2008
    Filing - Comments

    Comments of the Retail Energy Supply Association to the Illinois Power Agency Procurement Plan, filed by Rowland & Moore LLP. (Electronic)
  • 10/03/2008
    Filing - Appearance

    Appearance on behalf of Midwest Generation, LLC and Edison Mission Marketing & Trading, Inc., filed by Attorney Rebecca Lauer. (Electronic)
  • 09/30/2008
    Filing - Appearance

    Appearance of the City of Chicago, filed. (Electronic)
  • 09/26/2008
    Filing - Petition to Intervene

    Verified Petition to Intervene of BlueStar Energy Services, Inc., filed. (Electronic)
  • 09/26/2008
    Filing - Comments

    Comments of the Ameren Illinois Utilities, filed. (Electronic)
  • 09/22/2008
    Filing - Petition to Intervene

    Petition to Intervene of Constellation NewEnergy, Inc. and Constellation Energy Commodities Group, Inc., filed. (electronic)
  • 09/12/2008
    Filing - Appearance

    Entry of Appearance filed by Central Illinois Light Company d/b/a AmerenCILCO, Central Illinois Public Service Company d/b/a AmerenCIPS and Illinois Power Company d/b/a AmerenIP. (electronic)
  • 09/12/2008
    Filing - Appearance

    Appearance of the People of the State of Illinois, filed. (electronic)
  • 09/10/2008
    Filing - Errata

    Errata (by Letter) to the Petition for Approval of Initial Procurement Plan, filed by Illinois Power Agency. (Electronic)
  • 09/10/2008
    Filing - Errata

    Corrected Errata (by Letter) to the Petition for Approval of Initial Procurement Plan, filed by Illinois Power Agency. (Electronic)
  • 09/10/2008
    Filing - Appearance

    Appearance of Dynegy Inc., filed. (Electronic)
  • 09/09/2008
    Filing - Appearance

    Appearance on behalf of Commonwealth Edison Company, filed. (Electronic)
  • 09/04/2008
    Filing - Petition/Application

    Petition for Approval of Initial Procurement Plan, filed by Illinois Power Agency. (Electronic)
  • 09/04/2008
    Service - Administrative Law Judge Ruling

    Notice of attached Ammended Administrative Law Judge's Procedural Ruling served electronically to parties.
  • 09/04/2008
    Service - Administrative Law Judge Ruling

    Notice of attached Administrative Law Judge's Procedural Ruling served electronically to parties.