Case Number: 08-0422

  • 08/14/2008
    Filing - Report

    Report - Verified Statement regarding an Approved Amendment to an Interconnection Agreement between Verizon North Inc. Verizon South Inc. and Madison River Communications LLC d/b/a Gallatin River Integrated Communications Solutions, filed. (Electronic)
  • 08/14/2008
    Service - Order

    Copy of Final Order served electronically to parties.
  • 08/13/2008
    Order Entered - Final

    Final Order entered.
  • 08/12/2008
    Transcript - Received

    Transcript - July 29, 2008, received.
  • 07/29/2008
    Hearing Report - Heard and Taken-Yes

    Heard by Administrative Law Judge Sainsot and Taken.
  • 07/29/2008
    Hearing Report - Exhibits

    e-Docket: Staff Exhibit 1 - Verified Statement of A. Olusanjo Omoniyi - entered into evidence as filed on e-Docket.
  • 07/29/2008
    Hearing Report - Administrative Law Judge Ruling

    Staff's Motion to have the Final Order reflect the correct d/b/a was granted.
  • 07/29/2008
    Transcript - Pending

    Transcript pending.
  • 07/21/2008
    Service - Notice

    Hearing scheduled for July 30, 2008 has been advanced by the Administrative Law Judge to July 29, 2008, in Chicago at 1:00 P.M. Parties advised electronically.
  • 07/15/2008
    Service - Setting/Prehearing Conference

    Set for hearing by the Administrative Law Judge on July 30, 2008, in Chicago at 1:00 P.M. Parties advised electronically.
  • 07/11/2008
    Filing - Petition/Application

    Joint Petition for Approval of an Agreement Amending the Terms of an Interconnection Agreement between Verizon North Inc. and Verizon South Inc. and Madison River Communications LLC d/b/a Gallatin River Integrated Communications Solutions, filed. (Electronic)