Case Number: 04-0777

  • 03/21/2005
    Filing - Report

    Report - Verified Statement Regarding an Approved Amendment to an Interconnection Agreement between Verizon North Inc., Verizon South Inc., and AT&T Communications of Illinois, Inc., filed. (Electronic)
  • 03/10/2005
    Service - Order

    Copy of Final Order served electronically to parties.
  • 03/09/2005
    Order Entered - Final

    Final Order entered.
  • 02/02/2005
    Transcript - Received

    Transcript - January 19, 2005, received.
  • 01/21/2005
    Service - Administrative Law Judge Ruling

    Notice given by the Administrative Law Judge that this matter was marked "Heard and Taken" on January 19, 2005. Notice also given that the hearing scheduled for January 26, 2005, in Chicago has been cancelled. Parties advised electronically.
  • 01/19/2005
    Hearing Report - Heard and Taken-Yes

    Heard by Administrative Law Judge Riley and Taken.
  • 01/19/2005
    Hearing Report - Exhibits

    e-Docket: Staff Exhibit 1 - Verified Statement of A. Olusanjo Omoniyi.
  • 01/19/2005
    Hearing Report - Administrative Law Judge Ruling

    Staff Exhibit 1, the Verified Statement of A. Olusanjo Omoniyi, is admitted into evidence on Motion of the ALJ.
  • 01/19/2005
    Transcript - Pending

    Transcript pending.
  • 01/07/2005
    Service - Setting/Prehearing Conference

    Set for hearing by the Administrative Law Judge January 19, 2005, in Chicago at 10:00 A.M. Parties advised electronically.
  • 12/14/2004
    Filing - Petition/Application

    Joint Petition for Approval of an Agreement Amending the Terms of an Interconnection Agreement between Verizon North Inc., Verizon South Inc., and AT&T Communications of Illinois, Inc., filed. (Electronic)