Case Number: 03-0387

  • 08/27/2003
    Filing - Report

    Report, Verified Statement regarding Interconnection Agreement between Illinois Bell Telephone Company (SBC Illinois) and AT&T Communications of Illinois, Inc., filed. (Hand Delivered)
  • 08/19/2003
    Order Entered - Final

    Final Order entered.
  • 08/19/2003
    Service - Order

    Copy of Final Order served electronically to parties.
  • 08/14/2003
    Transcript - Received

    Transcript - July 17, 2003, received.
  • 07/17/2003
    Hearing Report - Heard and Taken-Yes

    Heard by Administrative Law Judge Zaban and Taken.
  • 07/17/2003
    Transcript - Pending

    Transcript pending.
  • 07/02/2003
    Service - Setting/Prehearing Conference

    Set for hearing July 17, 2003, in Chicago, at 10:30 A.M.; parties advised electronically.
  • 06/11/2003
    Filing - Petition/Application

    Joint Petition for Approval of Eighth Amendment to the Interconnection Agreement Between AT&T Communications of Illinois, Inc. and Illinois Bell Telephone Company (SBC Illinois), filed. (Electronic)