  • 05/02/2003
    Filing - Report

    Report - Verified Statement regarding Interconnection Agreement between Gallatin River Communications L.L.C. and Nextel West Corp., filed. (Hand Delivered)
  • 04/25/2003
    Transcript - Received

    Transcript - April 9, 2003, received.
  • 04/24/2003
    Service - Order

    Copy of Final Order served electronically to parties.
  • 04/23/2003
    Order Entered - Final

    Final Order entered.
  • 04/09/2003
    Hearing Report - Heard and Taken-Yes

    Heard by Administrative Law Judge Albers and Taken.
  • 04/09/2003
    Hearing Report - Exhibits

    e-Docket: Staff Exhibit 1 - Verified Statement of Staff, A. Olusanjo Omoniyi, filed on April 8, 2003.
  • 04/09/2003
    Transcript - Pending

    Transcript pending.
  • 03/28/2003
    Service - Setting/Prehearing Conference

    Set for hearing April 9, 2003, in Springfield at 10:00 A.M. Parties advised electronically.
  • 03/20/2003
    Filing - Petition/Application

    Joint Petition for Approval of Negotiated