Case Number: 03-0172

PLEASE NOTE: If testimony is pre-filed, it does not automatically become part of the official evidentiary record. It becomes part of the official record only if it is admitted without alteration into evidence by ruling of the Administrative Law Judge. The admission into evidence of electronically pre-filed testimony will be reflected on the docket sheet portion of e-Docket.
  • 05/16/2003
    Report - Interconnection Agreement

    Report - Verified Statement regarding Interconnection Agreement between Illinois Bell Telephone Company and Kentucky Data Link, Inc. d/b/a Cinergy Networks
    Mark A. Kerber
  • 05/08/2003
    Memorandum to the Commission

    Memorandum to the Commission
    Ian Brodsky
  • 05/08/2003
    Affidavit

    Affidavit
    Elizabeth A. Rolando
  • 05/07/2003
    Order - Final

    Final Order
    Ian Brodsky
  • 05/07/2003
    Voting Record

    Voting Record
    Ian Brodsky
  • 04/29/2003
    Transcript

    Transcript - April 9, 2003
    Mark Johnsen
  • 04/19/2003
    Exhibits

    Exhibits on behalf of Kentucky Data Link
    Court Reporter
  • 04/15/2003
    Notice of Administrative Law Judge Ruling

    Notice of Administrative Law Judge's Ruling
    Ian Brodsky
  • 04/11/2003
    Verified Statement

    Verified Statement of the Staff of the Illinois Commerce Commission
    James Weging
  • 04/10/2003
    Notice of Continuance

    Notice of Continuance
    Ian Brodsky
  • 03/28/2003
    Notice of Setting

    Setting Notice
    Ian Brodsky
  • 03/12/2003
    Signatures/Verification

    Verifications to Joint Petition for Approval of Negotiated Interconnection Agreement between Kentucky Data Link, Inc. d/b/a Cinergy Networks and Illinois Bell Telephone Company (SBC Illinois)
    Mark A. Kerber
  • 03/12/2003
    Petition/Application

    Joint Petition for Approval of Negotiated Interconnection Agreement between Kentucky Data Link, Inc. d/b/a Cinergy Networks and Illinois Bell Telephone Company (SBC Illinois)
    Mark A. Kerber