Case Number: T13-0065

  • 10/28/2014
    Filing - Notice

    Final inspection provided by staff – 9/30/14.
  • 04/21/2014
    Filing - Compliance

    U.S. DOT AAR Crossing Inventory Report – completion notice (3/12/14) electronically filed by Richard Ellison for UP.
  • 04/03/2014
    Filing - Compliance

    Completion Report electronically filed by staff for Union County.
  • 01/24/2014
    Filing - Report

    Progress report – signal installation has started, electronically filed by staff for UP.
  • 01/09/2014
    Filing - Report

    Progress report – approximately 90% of approach work complete, electronically filed by staff for Kevin Grammer, Union County Highway Engineer.
  • 07/26/2013
    Order Entered - X Resolution

    Copy of X-resolution (X-13550) approved July 25, 2013, mailed to Mr. Omer Osman, Director of Highways – IDOT, ATTN: Jason Johnson; Mr. Mack H. Shumate, Jr., UP; C T Corporation System, UP; Mr. Dave McKernan, UP; Mr. Richard Ellison, UP; Ms. Claire Anderson, UP; Mr. Kevin E. Grammer, Union County Highway Engineer.
  • 07/23/2013
    Filing - Form 3

    Copy of Form 3 (X-13550) electronically filed by Richard Ellison for UP.
  • 07/22/2013
    Filing - Compliance

    Completion Report (temporary STOP signs installed 7/18/13) filed by Richard Ellison for Union Pacific Railroad Company.
  • 07/10/2013
    Order Entered - Final

    Copy of Order and Stipulated Agreement entered July 10, 2013 mailed to All Parties of Record.
  • 06/20/2013
    Filing - Stipulated Agreement

    Stipulated Agreement #1733 filed.
  • 06/20/2013
    Filing - Compliance

    Project status report providing employee contact for project (Dave McKernan, UP 314-331-0682 dwmckern@up.com and Kevin Grammer, Union County Highway Engineer 618-833-2912 unioncohd@gmail.com) filed with the stipulated agreement.