    Filing - Report

    Progress report – scheduled start March 2014, electronically filed by staff for UP.
  • 01/22/2014
    Order Entered - X Resolution

    Copy of X-resolution’s (X-13586 and X-13587) approved January 22, 2014, mailed to Mr. Omer Osman, Director of Highways – IDOT, ATTN: Jason Johnson; Mr. Mack H. Shumate, Jr., UP; C T Corporation System, UP; Mr. Lance Kippen, UP; Mr. Richard Ellison, UP; Ms. Claire Anderson, UP; Mr. James E. Crane, Douglas County Highway Engineer; Mr. Steve Jones, Highway Commissioner, Camargo Township Road District.
  • 01/14/2014
    Filing - Form 3

    Copy of Form 3’s (X-13586 167007L and X-13587 167008T) electronically filed by Richard Ellison for UP.
  • 01/13/2014
    Filing - Notice

    Progress report – work to begin/resume after 4/1/14 or as weather permits, electronically filed by staff for Steve Jones, Camargo Township Highway Commissioner.
  • 07/17/2013
    Filing - Compliance

    U.S. DOT AAR Crossing Inventory Form – temporary stop signs (167007L and 167008T) filed by Richard Ellison for UP.
  • 07/10/2013
    Order Entered - Final

    Copy of Order and Stipulated Agreement entered July 10, 2013 mailed to All Parties of Record.
  • 05/28/2013
    Filing - Stipulated Agreement

    Stipulated Agreement #1707 filed.
  • 05/28/2013
    Filing - Compliance

    Project status report providing employee contact for project (Dave McKernan, UP 314-331-0682 dwmckern@up.com and Steve Jones, Highway Commissioner, Camargo Township Road District 217-493-8518) filed with the stipulated agreement.