Case Number: 13-0643

  • 12/20/2013
    Transcript - Received

    Transcript - December 4, 2013, received.
  • 12/19/2013
    Service - Order

    Copy of Final Order served electronically to parties.
  • 12/18/2013
    Order Entered - Final

    Final Order entered.
  • 12/04/2013
    Hearing Report - Heard and Taken-Yes

    Heard by Administrative Law Judge Haloulos Baker and Taken.
  • 12/04/2013
    Hearing Report - Exhibits

    Staff Exhibit 1 entered into record (verified statement)
  • 12/04/2013
    Transcript - Pending

    Transcript pending.
  • 11/22/2013
    Service - Setting/Prehearing Conference

    Set for hearing by the Administrative Law Judge for December 4, 2013, in Chicago, at 11:45 A.M. Notice served electronically to parties.
  • 11/18/2013
    Filing - Petition/Application

    Application for Certification as an Installer of Distributed Generation Facilities, filed by Title Electric Company. (mailed by USPS - November 15, 2013)