Case Number: 10-0422

  • 09/16/2010
    Filing - Report

    Report - Verified Statement regarding Approved Interconnection Agreement between Verizon North Inc. and Verizon South Inc., filed. (electronic)

  • 09/10/2010
    Service - Order

    Copy of Final Order served electronically to parties.
  • 09/09/2010
    Order Entered - Final

    Final Order entered.
  • 08/18/2010
    Transcript - Received

    Transcript - August 4, 2010, received.
  • 08/04/2010
    Hearing Report - Heard and Taken-Yes

    Heard by Administrative Law Judge Teague and Taken.
  • 08/04/2010
    Hearing Report - Exhibits

    Staff Exhibit 1 - Verified Statement of A. Olusanjo Omoniyi (filed on August 3, 2010)
  • 08/04/2010
    Transcript - Pending

    Transcript pending.
  • 07/20/2010
    Service - Hearing Continuance Letter

    Hearing scheduled for July 27, 2010 has been continued by the Administrative Law Judge to August 4, 2010, in Chicago at 11:10 A.M. Parties advised electronically.
  • 07/13/2010
    Service - Setting/Prehearing Conference

    Set for hearing by the Administrative Law Judge on July 27, 2010, in Chicago at 11:10 A.M. Parties advised electronically.
  • 06/29/2010
    Filing - Petition/Application

    Joint Petition for Approval of an Interconnection Agreement Between Verizon North Inc. and Verizon South Inc. and Cincinnati Bell Any Distance Inc., filed. (Electronic)