Case Number: 04-0484

  • 10/12/2004
    Filing - Report

    Report - Verified Statement regarding the Approved First Amendment to the Interconnection Agreement between Illinois Bell Telephone Company (SBC Illinois) and Home TeleNetworks, Inc., filed. (Electronic)
  • 10/07/2004
    Service - Order

    Copy of Final Order served electronically to parties.
  • 10/06/2004
    Order Entered - Final

    Final Order entered.
  • 09/09/2004
    Transcript - Received

    Transcript - August 25, 2004, received.
  • 08/25/2004
    Hearing Report - Heard and Taken-Yes

    Heard by Administrative Law Judge Riley and Taken.
  • 08/25/2004
    Hearing Report - Exhibits

    e-Docket: Staff Exhibit 1 - Verified Statement of Torsten Clausen.
  • 08/25/2004
    Transcript - Pending

    Transcript pending.
  • 07/30/2004
    Service - Setting/Prehearing Conference

    Set for hearing by the Administrative Law Judge on August 25, 2004, in Chicago, at 10:00 A.M. Parties served electronically.
  • 07/26/2004
    Filing - Petition/Application

    Joint Petition for approval of 1st Amendment to Interconnection Agreement between Home TeleNetworks, Inc. and SBC Illinois, filed. (electronic)