Case Number: 03-0206

  • 05/22/2003
    Service - Order

    Copy of Final Order served electronically to parties.
  • 05/21/2003
    Order Entered - Final

    Final Order entered.
  • 04/28/2003
    Transcript - Received

    Transcript - April 10, 2003, received.
  • 04/15/2003
    Service - Administrative Law Judge Ruling

    Notice of Administrative Law Judge's Ruling served electronically to parties advising that the above entitled matter was marked "Heard and Taken" by the Administrative Law Judge on April 15, 2003. Notice is also given that the hearing scheduled for April 24, 2003, at the offices of the Commission, Chicago, Illinois, has been cancelled.
  • 04/14/2003
    Service - Hearing Continuance Letter

    Parties advised electronically of continuance of hearing to April 24, 2003, in Chicago, at 3:00 P.M.
  • 04/10/2003
    Hearing Report - Heard and Continued

    Heard by Administrative Law Judge Brodsky and continued to April 24, 2003, in Chicago, at 3:00 P.M.
  • 04/10/2003
    Hearing Report - Exhibits

    e-Docket: Applicant Exhibit 1 - Application of C III Ops.
  • 04/10/2003
    Hearing Report - Exhibits

    Applicant Exhibit 2 - Testimony of Kim Larsen.
  • 04/10/2003
    Transcript - Pending

    Transcript pending.
  • 03/31/2003
    Service - Setting/Prehearing Conference

    Set for hearing April 10, 2003, in Chicago at 10:00 A.M. Notice also given that the Applicant should contact the Administrative Law Judge if it seeks to appear at the hearing by telephone. Parties advised electronically.
  • 03/27/2003
    Filing - Petition/Application

    Application for a Certificate to become a Telecommunications Carrier, filed by Mintz Levin Cohn Ferris Glovsky and Popeo, P.C. on behalf of C III Communications Operations, LLC. (mailed by USPS - March 24, 2003)